Facts

The MaineDOT would like you to believe that a “hard look at Route 9” was all it took – after ten years of work – that an alternative that met only 20% (1 of 5) of the purpose and needs in April 2009 was suddenly the best alternative for this connector with any and all presentation of documented facts by private citizens to refute the 2B-2 selection purposely obscured by their (MaineDOT) own definition of the word “substantive”.

A “hard look” alone does not and cannot erase the existing 148 existing access points and 10 existing roads that this connector now inherits, with 5 different posted speed limit changes over that 4.5 mile section of Route 9 now integral to 2B-2 with 158 possible left turns (left turns identified by the FHWA as increasing the chance of an accident by 7% per additional access point added to a rural highway and 2B-2 starts with 158 access points), and the fact that this connector also inherits the Village of East Eddington and its 35 mph speed limit.

If all of this is going over your head and you still want to make this a nimby issue, answer this one question: If you were tasked to provide this area with a real solution to get the logging trucks off of Route 46, a truck route starting in the Village of East Eddington, would you continue through and past the Village or would you bypass the Village and the 4.5 miles of Route 9 as was the reason behind the original and still valid system linkage need which 2B-2 fails to meet? You don’t even have to get into whether or not Route 46 is or is not an issue to answer that question and by the way – the mill is dead – no more logging trucks are going to the Bucksport Mill, yet suddenly the latest worry is all that Canadian truck traffic and Canadian tourists – REALLY?

Don’t let the MaineDOT/FHWA continue to hide the facts and control the conversation.

12.7.2015 b Capture

Click links below or from the header menu ribbon:

LD47 Testimony from LA

LD47 Testimony from GH

STIP Comments from GH

STIP Comments from LA

BACTS Testimony from LA

BACTS Testimony from SB

Substantive 2B-2 Facts

Letter to the OIG

Brewer Boondoggle

History was dismissed…

We have no money!!

LD783 Testimony from LS

LD783 Testimony from LA

A Viable Solution

Ides of March 2020

What’s the Real Cost?

Virtual Meeting Aug. 2020

Strong Towns Article

 

MaineDOT established that the preferred alternative (2B-2) for the I-395/Route 9 Connector did not meet the Study Purpose, the USACE Purpose, the System Linkage Need and the Traffic Congestion Need in April 2009, satisfying only 20% of the five Purpose and Needs. How this became a $124 million project was never satisfactorily answered. The 2024 MaineDOT Work Plan states: “[The] Mills administration...set the minimum unmet state capital transportation funding need at $200 million per year...MaineDOT has sufficient resources for the next two years...in the third year...and beyond, we will need to find other solutions for at least half of this annual need, now estimated at $100 million.” ($200 million in 2026.) This project’s $124 million would have been better spent on Maine’s annual unfunded transportation needs. (2.13.2024)

“It’s an emotional issue. We don’t need to settle this with them right away.” A condescending statement by MTA Peter Mills (PPH 3.21.2024)

As of February 18, 2024, informaton has been added on the Gorham Connector, a project much like the I-395/Route 9 Connector that my community has experienced for 24 years. Both are boondoggles, throwing hundreds of millions of critical transportation dollars of new pavement and steel at a problem without seriously considering cheaper alternatives to existing infrastructure, at a time when we can't afford to maintain the roads and bridges we already have. Maintaining roads and bridges is not "sexy", transportation officials that demand these boondoggles and the politicians that fund them just love ribbon cutting ceremonies.