The first I-395/Route 9 Transportation Study biweekly project status update was issued on 2 November 2012. It should be noted that the PAC has not been paneled since the last PAC meeting of April 15, 2009; after almost 7 years of inactivity there is essentially no such thing as a Public Advisory Committee – it simply does not exist…
161 weeks have gone by with the possibility of 80 updates if provided biweekly as we were promised. Gretchen had to request many of the last updates occurring over the past year or so. Below you will find 24 reports, far below the 80 that should/could have been provided. One may use the excuse that there was nothing to report, but when you are faced with the unknown – as we have been over the past 15 years – even a report of inactivity would have been helpful. This is just another example of a failed process. (December 8, 2015)
7.06.2017: An update from the MDOT – the first update since July 2016; I believe this is at least the 6th project manager since 2000. And – this one thinks we actually support this project!!
..
9/30/2016: This letter was sent to those unfortunate residents in direct assault by this project that are losing their homes and some or all of their land and those that abut the right-of-way of the 2B-2 alternative. A POR form was attached (available upon request) looking for data, most of which is obtainable by anyone at any city or town hall, so I’m not feeling much of an obligation to assist the MaineDOT at this time…
..
7.12.2016: Project status update from MaineDOT:
..
..
6.24.2016: The latest update from MaineDOT. The ROD is out:
..
Click here to view Record of Decision.
5.27.2016: Latest from the MaineDOT.
..
4.15.2016: The latest status update from the MaineDOT.
..
2.11.2016 – The latest update from the MaineDOT:
..
11.19.2015: Latest update from the MaineDOT.
9/15/2015: The latest MaineDOT Status Update.
7/29/2015: We are about to have the fifth MaineDOT Project Manager for this Study per the latest Status Update. The update is that there is no update…
6/8/2015: Latest project status update from the MaineDOT. Updates come few and far between and we really appreciate when they do come. However, if you look at the Study Update from June 8th and compare it to the Study Update from April 21st – what has really changed? Why is this taking so long?
MaineDOT project status report dated 6.08.2015
4/24/2015: Gretchen asked the MaineDOT for a project update and received this response from the project manager:
16 July 2014 email – it has been six months since an official MaineDOT Status Update. What is taking the USFWS so long to release their Biological Opinion when we have FOAA documents that indicate otherwise?
The first and last biweekly study update
13 June 2014 email – five months have gone by without an official MaineDOT biweekly study update. Why did these updates stop?
21 January 2014 email – my thoughts about the latest MaineDOT status report; the project is not in the current MaineDOT 3 year Work Plan, but what does that really mean?
I-395/Route 9 Connector Study Biweekly Status Report
26 April 2013 email and document – presenting more FOAA evidence to rebuke the MaineDOT Status Report of 19 April 2013.
I-395/Route 9 Transportation Study Status Update on 14 Mar 2014
Not an official update; request made by the Town of Eddington after 54 days of silence since last “biweekly” update.
I-395/Route 9 Transportation Study Status Update on 17 Jan 2014
I-395/Route 9 Transportation Study Status Update on 20 Dec 2013
I-395/Route 9 Transportation Study Status Update on 22 Nov2013
I-395/Route 9 Transportation Study Status Update on 25 Oct 2013
I-395/Route 9 Transportation Study Status Update on 11 Oct 2013
I-395/Route 9 Transportation Study Status Update on 30 Aug 2013
I-395/Route 9 Transportation Study Status Update on 1 Aug 2013
I-395/Route 9 Transportation Study Status Update on 19 Jul 2013
I-395/Route 9 Transportation Study Status Update on 28 Jun 2013
I-395/Route 9 Transportation Study Status Update on 3 May 2013
I-395/Route 9 Transportation Study Status Update on 19 Apr 2013
I-395/Route 9 Transportation Study Status Update on 22 Feb 2013
I-395/Route 9 Transportation Study Status Update on 11 Jan 2013
I-395/Route 9 Transportation Study Status Update on 2 Nov 2012
I-395/Route 9 Transportation Study Status update on 2 Mar 2011
Not part of the official updates, but my first request for an update via email on 2 March 2011. It needs to be noted that this Study was turned on its head by September 2010 and the Project Manager took it upon herself to withhold that critical information from me. To date, not one MaineDOT official has come forward to answer to or even acknowledge this manager’s unethical and deliberate action; that email is part of the Responses to Substantive Comments document and of course it wasn’t deemed substantive enough for an official comment. (L Adams)